8th September 2021 - Fosterville Gold Mine issues updated community notification for exploration activities at Robbins Hill. *Full .pdf attached at the bottom of the page outling the details and view a map of the area.
We write to you today on behalf of Fosterville Gold Mine (FGM), to update you on current and proposed exploration activities in the vicinity of your property. These activities are the continuation of the Robbins Hill exploration program, with original correspondence sent on the 7 January 2021.
Please find the attached .pdf to see a map which outlines both current exploration drill sites and future exploration drill sites.
Diamond drilling utilises a hollow drill bit impregnated by diamonds to produce a ‘stick’ of core that preserves details of geology, ground conditions and mineralogy. The diamond drill rig will be operated by two to three personnel, with occasional visitors, as required. Access to all drill sites will be via internal site roads, with access via public roads only if required. Expected time frames for the exploration drilling are outlined below, however this will be subject to minor variations depending on ground conditions and operational requirements.
Current Exploration Drilling
Site A – Exploration diamond drilling until mid-November (noise attenuation to be considered subject
to monitoring results)
Site B – Exploration diamond drilling until early October (noise attenuation to be considered subject to monitoring results)
Site C – Exploration diamond drilling within custom built acoustic shed until mid-November
Site D – Exploration diamond drilling with installation of sound attenuation panels until mid-November
Site E – Exploration diamond drilling within custom built acoustic shed until early December
Learn more about Diamond Drilling
Future Exploration Drilling
Site F – Exploration diamond drilling within custom built acoustic shed. Commencing mid November until late December
Site G & H – Exploration diamond drilling at either site within custom built acoustic shed. Commencing early October until late January 2022.
Drilling will commence during daytime (7:00am-6:00pm) operating hours, with the intent to extend to continuous drilling (24/7) subject to noise monitoring results and community feedback. Day shift operating hours are 7:00am to 6:30pm and nightshift extends from 7:00pm to 6:30am.
During start up and throughout the drilling program, FGM personnel will conduct periodic noise monitoring at the site and closest receptors to ensure compliance with regulatory noise limits is maintained. Noise monitoring will be conducted during daytime (7:00am-6:00pm), evening (6:00pm10:00pm) and nighttime (10:00pm-7:00am) periods. Noise monitoring will involve an appropriately trained FGM representative (or contractor) accessing nearby receptors for a period (15-30 minutes) to record noise levels using a calibrated sound meter. Monitoring will assess noise levels from both individual drill rigs and the cumulative contribution of the various rigs operating throughout the program. If you would like noise monitoring to be undertaken at your property please contact a member of the FGM Community Team to have this arranged.
Upon completion, the drill holes will be grouted to 1 m below surface and then backfilled with native soil/material from the site. The drill pad area and any vehicle access tracks will be rehabilitated to return the site to its initial condition. Additional information regarding the abandonment of mineral drillholes can be found on the Earth Resources website earthresources.vic.gov.au
This letter is to ensure nearby landholders remain informed of FGM’s exploration activities. FGM aims to minimise any adverse impacts from our operations and exploration activities on nearby residents.
Should you have any questions or concerns regarding the information provided in this letter, please contact FGM’s Community Team on 03 5439 9000 or email fgm.community@kl.gold